Yes. Sacramento County RHIP requires an SB 721 inspection report as part of its inspection process for properties covered by the law. North American Construction Services provides SB 721 inspections for rental property owners. This guide explains the County’s SB 721 report requirements, how the report differs from the regular RHIP checklist, and what to do when repairs are needed.
What does Sacramento County RHIP cover?
Sacramento County’s Rental Housing Inspection Program, or RHIP, covers residential rental properties in the county’s unincorporated area. Its purpose is to check housing conditions and address health and safety violations. The County describes registration, self-certification and audit procedures on its RHIP program page.
The City of Sacramento operates a separate rental inspection program. Use the property’s governing jurisdiction, not just the city name in its mailing address, to identify the correct office.
RHIP and SB 721 also have different scopes. A rental can fall under RHIP without having the elevated structures that trigger SB 721.
Which properties need an SB 721 inspection?
SB 721 applies to buildings outside common interest developments that contain three or more multifamily dwelling units with qualifying exterior elevated elements. Those elements include balconies, decks, porches, stairs, walkways and entry structures, together with their supports and railings.
Under Health and Safety Code §17973(a)–(b), the structures must extend beyond the exterior walls, be designed for people to use, and meet both conditions below:
- The walking surface is more than six feet above ground level.
- Wood or wood-based products provide all or a substantial part of their structural support or stability.
The height of the walking surface matters. The law does not add a six-foot minimum balcony length. A concrete walking surface also does not establish an exemption if wood provides all or a substantial part of its structural support.
The inspection covers the load-bearing parts, which carry the structure’s weight, and the waterproofing that protects them. A qualified inspector evaluates the building and identifies the covered elements. Our California SB 721 inspection guide explains the broader inspection requirements.
The RHIP checklist and SB 721 report are different documents
Completing the ordinary RHIP checklist does not replace the inspection and report required by SB 721. The County’s checklist and the statutory report serve different purposes.
The RHIP Exterior Inspection Checklist includes stairs, balconies and exterior walkways. It tells owners to give a copy of that form to the tenant, keep a copy, and not send copies to Code Enforcement. That instruction concerns the checklist itself.
Owners of applicable properties must submit the separate SB 721 inspection report to RHIP. The statute requires a signed or stamped report with photos, test results where applicable, and a written account of the inspected components. It also allows local enforcement agencies to require initial reports, final reports, or both. See §17973(c)–(d).
Keep the checklist and the SB 721 report as separate records. A checked box for a balcony does not document the full SB 721 evaluation.
Does the County perform SB 721 inspections?
No. Owners must hire an independent, qualified inspector for SB 721. Sacramento County does not provide that service, although it does conduct inspections and audits under its regular RHIP program.
Section 17973(a) identifies the eligible inspectors:
- A licensed architect, civil engineer or structural engineer.
- An A, B or C-5 licensed contractor with at least five years of experience, while holding the qualifying license, constructing multistory wood-frame buildings.
- A person certified as a building inspector or building official by a recognized association, as determined by the local jurisdiction.
The statute says these individuals cannot be employed by the local jurisdiction while performing these inspections. A standard RHIP self-certification course does not by itself establish those qualifications.
When arranging an inspection, ask who will perform it and which statutory qualification that person meets. Provide the RHIP notice so the inspector can account for any property-specific reporting instructions.
How does RHIP review the report, and when is it due?
The report goes to RHIP for review by a Senior Code Enforcement Officer.
Use the submission instructions in your property’s RHIP notice. If the notice does not give a date or delivery method, ask RHIP to provide those details for your property. The County’s RHIP contact information is listed on its program page.
Several separate clocks can affect the same property:
| Document or action | Timing and responsible party |
| Ordinary SB 721 report delivered to the owner or designated agent | The inspector provides the signed or stamped report within 45 days after completing the inspection. |
| Report recommending immediate repairs, identifying an immediate safety threat, or requiring access restrictions or emergency repairs | The inspector provides a copy to both the owner and local enforcement agency within 15 days after completing the report. |
| Routine submission to County RHIP | Submission is required for applicable properties. Follow the filing instructions in your property’s RHIP notice, or ask RHIP for the due date and delivery method. |
| Nonemergency corrective work | The owner applies for a permit within 120 days of receiving the report. Repairs follow within 120 days after permit approval, unless the local enforcement agency grants an extension. |
| Immediate safety measures | The owner acts immediately when the inspector identifies an emergency condition. |
The statutory timeframes above come from §17973(c), (d) and (h). The 15-day reporting rule does not give an owner 15 days to leave an unsafe balcony open.
What happens if the report calls for repairs?
RHIP will refer reports identifying conditions requiring immediate repairs to the Sacramento County Building Department for further evaluation. That referral is separate from the owner’s duty to act on an emergency condition.
Under §17973(g)–(h), the owner must take the required preventive measures immediately. Preventing access until emergency repairs can be completed satisfies that immediate-measures provision. Emergency repairs must be inspected by the inspector and reported to the local enforcement agency.
For repair planning, give the contractor the complete report, marked photos and any County notices. The written scope should identify each affected assembly, the specified repairs and any further evaluation needed. Required permits must be obtained, and the work must be performed by a qualified, licensed contractor in accordance with the inspector’s recommendations and applicable requirements.
A separate contractor for SB repairs throughout California
Good Life Construction provides SB 721 repairs and SB 326 repairs throughout California. Good Life Construction is a separate Good Life Group company that performs the repair construction. North American Construction Services provides inspections; owners remain free to choose any qualified, licensed repair contractor.
Good Life Construction’s Stockton balcony replacement project involved 140 rear balcony assemblies. The project record describes damaged framing and further damage found near water-heater closet walls and roof sheathing. That repair example shows why the written scope may need to account for concealed damage beyond the walking surface.
Common questions about SB 721 and rental properties
The first inspection deadline and the type of property ownership affect which requirements apply. Keep those questions separate from the County’s report-submission process.
Has the SB 721 inspection deadline passed?
The general first inspection deadline was January 1, 2026, followed by inspections by January 1 every six years. For buildings with permit applications submitted on or after January 1, 2019, the first inspection must occur no later than six years after the local jurisdiction issues the certificate of occupancy.
The current law also provides extra time when confirmed asbestos-containing material prevents completion of the inspection: up to nine months for the necessary lawful abatement, then no more than three months to complete the inspection. The owner must keep records confirming the material and its abatement for three years after the inspection. These provisions are in §17973(d)–(f); they do not create a general extension for every rental property.
What is the difference between SB 721 and SB 326?
SB 721’s inspection section excludes common interest developments, as defined in Civil Code §4100. Such properties have a separate legal framework, so renting out a condo does not automatically place the building under SB 721. See §17973(n) and our SB 326 inspection guide for HOAs.
Arrange an SB 721 inspection for your rental property